The Tivoli project comprises the building of 270 subsidized apartments for owner occupation, 123 social housing units, some commercial spaces, two day care centers and a small workshop for the Brussels cleaning services. The project also comprises the construction of the local roads. The sustainable nature of the district is set by a starters center for businesses in the environmental field, very high energy efficiency of the houses and buildings, roads constructed in view of pedestrians and cyclists, attention to permeability of the soil and water resources management, as well as green zones and improvement of the biodiversity.

Be sure to check out the timelapse for the evolution from July to December 2017.

building site

Rue du Tivoli - Rue de Molenbeek - Rue Claessens, Brussels

client

PARBAM

architect

  • TH Adriana

main contractor

  • BAM Contractors
  • Besix
  • CFE

floor surface

57.133 m²

building time

site start: September 2016
site end: June 2019